Granny Flat Construction
Home » Thoughts and Opinions » Granny Flat Construction
Here’s a little photo gallery of the progress of the granny flat.
21 Apr 2023 holes for granny flat foundations
27 Apr 2023 granny flat foundations in place
1 May 2023 granny flat subfloor delivered
8 May 2023 granny flat roof trusses delivered
16 May 2023 granny flat subfloor
19 May 2023 granny flat walls, windows and doors delivered
25 May 2023 granny flat subfloor completed
26 May 2023 granny flat frame up
29 May 2023 granny flat rood trusses up
1 June 2023 granny flat scaffolding in and plumbing in
1 June 2023 granny flat roof delivered
2 June 2023 granny flat flooring delivered
5 June 2023 more granny flat plumbing
8 June 2023 granny flar roof i on!
9 June 2023 first fix electrics
16 June shower drainage
21 June roofing
22 June wall cadding
22 June wall wrapping
24 June insulation
27 June outer cladding
1 July window frames
2 July interior cladding
8 July first skip
11 July kitchen
27 July bathroom
27 July bathroom
1 August started painting
2 August finished painting
10 August ember protection
14 August flooring
16 August Step
17 Ausgust water heater & tanks
17 August wardrobe
17 August plumbing fixtures
22 August rubbish to remove